A Global Chemical Company Uses Lean, Predictive Analytics, and Capital Best Practices to Accelerate Schedule and Cost Improvement
Client Context
- A global pure play, integrated lithium company with annual revenues of ~$440 million, producing battery grade lithium hydroxide for Energy Storage & Battery Systems serving the Aerospace Pharmaceutical and Agrochemicals industries.
- The company required accelerating and optimizing an ambitious > $300 million Capex program to double the size of operations.
Key Challenges
Compounding the challenge of the investment program was a complex multi-country execution plan with Engineering taking place in Thailand, Procurement and Module Fabrication centered in China and Construction and Production located in South America. Key Challenges were:
- Lack of understanding of size and complexity of the project and the need for the entire company to come together to support from HR to Site Leadership.
- Lack of processes to bring a global team together to make decisions, resolve issues, and escalation.
- Lack of an integrated analytics platform to track real time progress and performance along the value chain
- Poor visibility and understanding of delays on each process as well as respective impact on program schedule and cost
- Weak vendor and interface management practice with interactions between key stakeholders and decisions made without data support and analysis
Approach & Key Success Factors
ARGO-EFESO and client leadership initiated a global leadership multi-day meeting to rapidly develop organization roles, responsibilities, and expectations; learned Lean Construction techniques; and completed pull planning for all major construction milestones. Implementation was across three continents and six countries. The following are the key solutions that were implemented:
- Developed global command center with Visual Management cadence on critical path milestones, Engineering and Design, Procurement, Financial Funding, Manufacturing Interface Management, Logistics Critical Path Analytics, Project Controls, and Construction Management.
- Implemented weekly and daily stand-up meetings at all levels including construction sites.
- Reviewed and optimized master schedule to reduce schedule by 12% and costs by 3%.
- Developed project control dashboards from corporate board level to construction vendor level.
- Implemented Critical Path Analytics Strategy & Model aligned to start up sequence which minimized schedule delays substantially. Included engineering, procurement, module manufacturing, shipping, customs, construction, and commissioning. The improved overall program predictability significantly.
- Implemented Interface Management between Engineering and Manufacturing, Manufacturing and Shipping, Shipping and Customs, Customs and Trucking, and Construction and Commissioning.
Results
8%
Improvement in schedule from original baseline
$27M
Savings in costs from procurement negotiations
60-70%
Schedule variation reduction
30%
Procure to pay lead time reduction
20%
Reduction PO days of delay
167
Number of critical path barriers mitigated or eliminated